Downtime Tracking

Mockup

Malisko Engineering, Inc was asked to provide a Downtime Tracking System to pinpoint sources of production inefficiencies and assist with prioritizing corrective maintenance planning. The System was designed, programmed, tested, installed, and validated for a worldwide leading manufacturer of Infant and Adult Nutritional Products.

Goals

  • Identify & Quantify Sources of Production Line Downtime
  • Provide "Root Cause" Information for Downtime
  • Provide both Real-time & Historic Data
  • Analysis via SQL (Structured Query Language) Database
  • Malisko Engineering, Inc. was involved in every aspect of this Project, from Conception and Capital Budgeting to Real Time Production

Challenges

  • Identify Possible Sources of Downtime Based on Empirical Study
  • Use Existing Sensors & Devices Only
  • Aggressive Project Schedule
  • Overcome Plant's Skepticism Due to Inaccuracies of Downtime Tracking Systems Previously Supplied by Others

System Features

  • Monitor Line from Can Depalletizer Through High-Speed Fillers/Seamers
  • Forty-two (42) Unique Causes Monitored
  • Log to Microsoft Access Database Each Line Stoppage Occurrence with the Following:
    • Root Cause
    • Date & Time of Occurrence
    • Elapsed Time of Stoppage
    • Batch Code
  • Production Line Number
  • Display Real-time Table of the Causes
    • By Production Line Number
    • By Equipment Section
    • Accumulative Number of Occurrences of Each Cause for the Batch
    • Accumulative Downtime of Each Cause for the Batch
  • Display Real-time Pareto Charts by Production Line Number & Equipment Section
  • Display Real-time Bar Charts of Accumulative Downtime of Each Cause by Line Section
  • Automatically Generate Hardcopy Downtime Summary Reports & Pareto Charts at the End of Each Batch
  • Can Generate Reports & Charts on Demand

Project Successes

  • Production & Maintenance Groups Immediately Started Using the Information
  • Efficiency Improvements were Quickly made by Addressing the Primary Culprits of Downtime
  • Achieved ALL Goals
  • System Installed in 1996 & Continues to be Used